Monday, January 21, 2013

What Makes a Good Estimating Model?

What makes a good estimating model?

It depends on the phase! A good estimating model in design phase or pre-construction phase?

Since BIMES is mostly involved in pre-construction phase, I would like to focus on this in this post:

1 - Model according to means and methods of construction:
The most important thing is doing the model according to the actual means and methods of the construction.   What do I mean?
Well, column height is the best example for this. You can model your columns as a single piece from bottom to top of the project. However in real life, the columns are constructed floor by floor. The right approach is modeling the columns floor by floor the way they are built. The start and end point of a column is also important. Is it from structural slab top to structural slab top or from structural slab top to structural slab bottom? You need to answer these kind of questions beofer starting the project.

2 - Model according to the output required:
You need to understand what output is required from the model before starting. Make sure that you understand it in detail. For instance, the concrete quantities! How to segregate it? Just a floor by floor element quantity might be enough! Or you might have to segregate it as per the concrete grade. Once you understand this, plan which information will be entered to which area? You can sort it by using layers or the custom IFC parameters introduced in ArchiCAD 16.
Image courtesy of adamr / FreeDigitalPhotos.net

3 - What should be modeled? What should NOT be modeled? 
An important decision that depends on 2 main factors:
  • Time allocated for modeling
  • Future use of the model
For instance, you are modeling for tender which means you have very limited time! So you have to model smartly. For instance you can model the exterior walls conceptually and use the exterior surface area only and make assumptions for the insulation etc. It would work very well if you bid for the project but don't get it:)

However if you get the project, you will have to provides details of the wall skins/sub-components for accurate estimates as well as shop drawings. You might think, I will just replace the wall or increase it's detail level but most of the case, remodeling would be preferred by the modeler.

In another case, if the model will be used only for coordination and quantities then you can work with abstract elements and attach unit costs.

So we usually have a kick off meeting before starting the project to discuss these details and draw a road map. This is very important for a successful and efficient BIM Modeling process.

Diyane Koseoglu
www.bimes.com






Tuesday, April 17, 2012

How to create Component List based on Concrete Grades in ArchiCAD?

Good Morning,

Image from Salvatore Vuono

I was planning to write more about contractual aspect of BIM in the projects but Jothi came up with a new video so I did not want to deprive you from his popular technical tips and tricks.

His latest video is also about quantities and schedules. He explains how to add concrete grades to the columns, beams and slabs.

I know many people uses Layers and IDs for this purpose but Jothi has a different approach. I am not sure which one is handier though. Please share your comments with us...


Enjoy!

Diyane Koseoglu
Jothi Shanmugam
www.bimes.com

Monday, April 9, 2012

Do you want to get more detailed quantities from ArchiCAD?

Do you want to get more detailed quantities from ArchiCAD?

Plaster, structural concrete, light weight concrete  and brick etc....
Image from Rawich

Then you should learn more about Interactive Schedules for Components.

Here comes a 10 minutes video from Jothi!

Enjoy!

Diyane Koseoglu
www.bimes.com

Wednesday, February 29, 2012

Decision Makers! Please do your homework about BIM!


The image above represents the Vico Engagement Plan in the USA.

In USA, it would take a contractor  9 weeks start with 4D and 5D BIM training or pilot project. I believe this is a very reasonable period if the decision makers do their homework.

What about in the Middle East? We usually spend 9 to 12 months introducing the software and 4D&5D process.

As you see the difference is huge! In USA it is 9 weeks and in the Middle East it is 48 weeks!

Why?

Unfortunately the decision makers don't do their homework in the Middle East! They mostly wait for spoon feeding!

Why?

Are they too busy? I don't think so! It's recession time. No company is overloaded with projects these days. (Except us :)))

Dear Decision Makers,

First watch our 5D BIM for Contractors Video please!

Please do your homework! Make sure that your team evaluates the software and process properly during the "Evaluation / Trial" period!

Evaluation period is the time when one of our implementation specialists is dedicated to anwser all your questions. Feel free to keep them busy;)

I will also appreciate if you do not call us asking directly for  a "BIM Quotation" :))

BIM is a process, not a tool! :)

Enjoy your weekend!
I hope we will not have any sandstorms! Cross your fingers:)

Diyane Koseoglu
www.bimes.com





Wednesday, February 1, 2012

Should quantity surveyors fear BIM?

Should quantity surveyors fear BIM?

They definitely do fear BIM but the questions is should they?

No, not at all!

I have been planning to write a post about this for quite a long time but always something else was poping up.

Until today:) I saw this as a discussion topic on LinkedIn.

As you know, I do not like reading long and boring stuff. I quickly skim the text and if it is really something to spend my time and energy I would read it carefully then.

And, the first comment on the discussion just stroke me!

Wow! If I was gonna write the blog post, it would be within the same lines with Gary Bowen's comment. (His English is better than me tough :))

Here comes his comment that I 100% agree:

"Quantity Surveyors "fearing BIM" is becoming an increasingly common statement to make, as the initial reaction to BIM is usually that the QS's job is threatened with automatic takeoff processes. But in practice, this is clearly not the case. A fundamental aspect which is rarely covered by those who bring up this, is, 'Where can the QS provide value for developers on BIM projects?'

Very few QS's provide value by quickly rattling off the automatically generated volume of concrete below grade for example. Whether it's a BIM or traditional project, the key deliverable of a QS does not change - therefore there is no need to fear BIM as no change in a process will replace that deliverable.

Even if the QS is provided with a full breakdown of quantities in the model, in practice, these are rarely in the format required for pricing. After formatting assemblies and schedules into standardized pricing formats like materformat or uniformat etc, only one stage has been achieved. I.e. Only the model has been measured and priced. This is not the required task a QS should focus on... A QS should provide value by pricing the 'project' and not the 'model' - i.e. what elements of the model are missing, how much risk should be applied, is the building an efficient shape, are life-cycle costing options a high importance on this project, is the cost plan amount expected to be the final construction cost etc etc. By reducing the time taken to compute the quantities, the QS can then focus on more billable hours by providing these services. Providing value for a facility will never be replaced by others automatically generating quantities.

Perhaps fearing the initial investment in upgrading computers & software to handle models may be a 'fear' for small-medium companies, but I assume your question refers to general implementation and processes. In short, people should embrace the new opportunities and look forward to overcoming some of the road-bumps on the way."


I hope you enjoyed it too!
Have a fabulous weekend!
Diyane Koseoglu